ID 609356

Archived

Durham Water Resource Recovery Facility (WRRF) Solids Building Drain Improvements, Tigard, OR

Washington County

Owner Reference: Project No. 7070

Bid Date: 12/16/2021 at 02:00pm

Pre-Bid: 12/07/2021
16580 SW 85th Avenue, Tigard, Oregon 97224

Estimate: $480,000

Trades: General Engineering Contractor GEC

Project consists of work that is generally described as follows (collectively, Work): 1. Install a cured-in-place pipe (CIPP) liner in an existing building drain line located in the basement tunnels, including cleaning and inspection of the main lines, laterals, and constructing necessary access pits. 2. Remove and replace the existing drain lateral and floor drains. 3. Remove existing drain cover grates and strainer baskets and replace with fabricated drain covers. 4. Installation of new drain cleanouts and sump manholes. 5. Remove and replace the existing cleanout covers. 6. Remove and replace the existing drain mud valves. 7. Extend an existing trench drain. 8. Perform final CCTV inspection and leak testing of completed Work. At Owner’s election, the Work will also include Contractor: 1. Installing a CIPP liner in two drain laterals connected to the Ferric Chloride Chemical Containment Area, 2. Replacing drain line laterals that are video inspected as part of the Work, but found to be in disrepair. Replacement shall be completed per Drawing Details 1/C005, 3/C005, and 1/S001. 

Bonds required.

Clean Water Services, OR

Michelle Mann
 (503) 547-8035
 Login or create an account To view email

Published 11/30/2021 on Construction Bid Source

DISCLAIMER: Projects posted by Construction Bid Source contain information that is aggregated daily from multiple sources. It is the individual responsibility of our members to contact the owner directly for purposes of bidding on a project and gaining additional project information. Construction Bid Source does not assume any responsibility for omissions or errors.