ID 555783

Archived

Plant Water Pipeline Replacement, Kinnison, Lindstorm & Scott Tunnels, Plant 2, Huntington Beach, CA

Orange County

Owner Reference: FE18-14

Bid Date: 10/19/2020 at 11:00AM

Pre-Bid: 09/24/2020
Virtual Pre-Bid Conference & Job Walk. Pre-Bid attendees may use either a computer, iOS or Android device to join the meeting. (Use link in the attached)

Estimate: $1,300,000

This project entails the replacement of about 2,600 feet of existing Plant Water piping and appurtenances in Scott, Kinnison, and Lindstrom Tunnels. Included are addition of new valves, replacement of existing valves, and reconnection of service lines. Replacement of piping will mainly be in the same place as the existing pipe. Project duration is 365 Calendar Days. Bonds required. Prevailing wages apply. Bonds required.

Orange County Sanitation District (OCSD)

Jay Kaura
 714.962.2411
 714.965.0728
 Login or create an account To view email

Published 09/10/2020 on Construction Bid Source

DISCLAIMER: Projects posted by Construction Bid Source contain information that is aggregated daily from multiple sources. It is the individual responsibility of our members to contact the owner directly for purposes of bidding on a project and gaining additional project information. Construction Bid Source does not assume any responsibility for omissions or errors.