ID 529062

Archived

Barren Ridge Switching Stn To Haskell Canyon Switching Stn Line 1 Upgrade Project, Santa Clarita, CA

Los Angeles County

Owner Reference: 90555

Bid Date: 03/31/2020 at 02:00pm

Pre-Bid: 03/03/2020
John Ferraro Building (JFB), 111 N Hope St, A - Level Auditorium, Los Angeles, CA 90012. There is also a mandatory site visit on Mar 4th & again another on Mar 5th. See attached. Dirt lot ust off Copper Hill Drive, 21430 Copper Hill Drive, Santa Clarita, CA 91390

Estimate: $121,000,000 to $152,000,000

Contractor shall demolish and haul away the remaining segments of the existing 51-mile Barren Ridge Switching Station to Haskell Canyon Switching Station Line 1 (BAR-HSK L1) conductors, ground wire, insulators hardware assemblies, structures and the tops of the footings between the Barren Ridge Switching Station and Haskell Canyon Switching Station. Contractor shall also engineer, design, procure, and construct new foundations and towers, install three (3) single Aluminum Conductor Steel Supported (ACSS) conductors; and install one (1) overhead ground wire from the Barren Ridge Switching Station to the Haskell Canyon Switching Station. Bonds required Prevailing wages apply.

Los Angeles Department of Water and Power

Jeremy Devore
 (213) 367-7526
 Login or create an account To view email

Published 02/17/2020 on Construction Bid Source

DISCLAIMER: Projects posted by Construction Bid Source contain information that is aggregated daily from multiple sources. It is the individual responsibility of our members to contact the owner directly for purposes of bidding on a project and gaining additional project information. Construction Bid Source does not assume any responsibility for omissions or errors.