Laurel Avenue Reconstruction Project, Sutter Co CA

Sutter County

Owner Reference: RR31001985R

Bid Date: 07/25/2019 at 10:00am

Estimate: $300,000 - $1.0M

The project consists of pulverizing the existing road bed and placing Hot Mix Asphalt Surfacing. The work includes ditch excavation, cold planning asphalt concrete, replace asphalt concrete surfacing, culvert installations and installation of new survey monuments. 25 working days.

County of Sutter, General Services, CA

Devlopment Svcs
 (530) 822-7400
 (530) 822-7109

Published 06/28/2019 on Construction Bid Source

DISCLAIMER: Projects posted by Construction Bid Source contain information that is aggregated daily from multiple sources. It is the individual responsibility of our members to contact the owner directly for purposes of bidding on a project and gaining additional project information. Construction Bid Source does not assume any responsibility for omissions or errors.