ID 580038

Archived

Clinton & Angus Improvements, Fresno, CA

Fresno County

Owner Reference: 3801

Bid Date: 04/20/2021 at 03:00PM

Estimate: $643,600

The scope of work includes installation of a traffic signal at the intersection, sidewalk reconstruction, accessible ramps, asphalt grind and overlay, and signage and striping. Project duration is 90 working days. Questions are due no later than 3:00 PM on Apr 13th. Bonds required. Prevailing wages apply. The mandatory participation level for National Targeted Workers is 15%.

City of Fresno CA

Sherri Cuadros
 (559) 621-1151
 Login or create an account To view email

Published 03/25/2021 on Construction Bid Source

DISCLAIMER: Projects posted by Construction Bid Source contain information that is aggregated daily from multiple sources. It is the individual responsibility of our members to contact the owner directly for purposes of bidding on a project and gaining additional project information. Construction Bid Source does not assume any responsibility for omissions or errors.