ID 554938

Archived

Windsong, Cedarbrook, and Park Avenue Street Rehabilitation Project Aliso Viejo,CA

Orange County

Bid Date: 09/22/2020 at 02:00pm

Estimate: $500,000

The work includes the following: grinding existing asphalt pavement (55,000 SF), placing asphalt concrete pavement with fibers (2,300 tons), curb ramp improvements, thermoplastic striping and markings, traffic control, and raising utility manholes, and utility valve covers. Bonds required. Prevailing wages.

City Of Aliso Viejo

Mitzi Ortiz
 949.425.2530

Published 09/06/2020 on Construction Bid Source

DISCLAIMER: Projects posted by Construction Bid Source contain information that is aggregated daily from multiple sources. It is the individual responsibility of our members to contact the owner directly for purposes of bidding on a project and gaining additional project information. Construction Bid Source does not assume any responsibility for omissions or errors.